cancel
Showing results for 
Search instead for 
Did you mean: 

Availablity check

Former Member
0 Kudos

Hi Experts,

Please any body light up on below issue.

If there is stock of the materials required to make Z i.e. X and Y Components, the availability check should report a fixed number of days to assembly, i.e. 2.

· If there us insufficient stock of the materials required to make Z, the availability check should report the longest lead time for the material which is short plus the a fixed number of days to assembly, i.e. 2.

is it possibe in SAP?

Regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

True ,Try with Total replenishment lead time in Material Master MRP3 view and AMintain for bot components and Higher level Item .

For further inputs contct your PP consultant ( Routing and Work Scheduling )

Former Member
0 Kudos

This is infact standard functionality. For example If Z is made up of two components X and Y and Componenet X takes 5 days of production time and component Y takes 3 days of Production time and 2 Days is for assembly then the Z's availability Lead time will be 5 + 2 = 7 days only.

Thanks,

Raja