Settings required to create Project in background from Sales Order creation

Former Member
0 Kudos

Dear Guruu2019s

Can you please explain what all the customizing settings that required to create Project in background from Sales Order creation.

Regards,

Sai

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

answered

Former Member
0 Kudos

Dear,

You will get one network per sales order line item as the result of assembely processing.

Regards.

Former Member
0 Kudos

Hi,

Steps for Assembly Processing,

create standard WBS CJ91

create standard Network CN01

Assign material (Finished) to standard network CN08.

from SD point ,

Create sales document type.

check requirement classes and requirement types from PS.

take KMPN and 212

for material in MM02 material master ,

Maintain view MRP3 Strategy group 85 Assembly processing with network/project.

Create Sales order va01,

then assign material to sales order.

and while saving it will Trigger project.

Regards,

Nitin Ghadge

nitin_patoliya
Active Contributor
0 Kudos

This is standard assembaly processing scenario.

Please chekc out this Thread. https://forums.sdn.sap.com/click.jspa?searchID=31532996&messageID=7914543

If you search in PS forum with assembaly processing you will get lots of material, use that for initial understanding,

With Regards

Nitin P.