Production Planning

Former Member
0 Kudos

How to activete single alternative BOM among multiple existing BOM.Thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Change the BOM status of BOM make it '02'

Regards,

Vishal

Former Member
0 Kudos

How to change the BOM status?

Former Member
0 Kudos

Hi,

Use t code Cs02

enter material

plant

alt BOM

on BOM header you will find the BOM status make it deactive

Regards,

Vishal

Former Member
0 Kudos

Thanks a lot.