09-11-2009 5:53 AM
Hello,
I wanted to check with you, have any of you defined criteria for Splitting the Document(PO OR STO) generated out of Replenishment Run(WRP1).
By default, SAP Generates new document at SITE+VENDOR in case of external PO.
Can we add additional criteria eg. Merchandise Category or a node from Article Hierarchy Structure?
If yes, how?
What was the impact on the processing time?
Rgds
Tapan
10-07-2009 2:29 PM
Hi Tapan,
If you want WRP1 should generate documents with a selected criteria ,you need to run with the required selection,for example if you want by merch.category,you a option of on selection screen of WRP1.similarly by article or by sites .you can set with a different selections .
Thanks,