Hi i have a scenario where in if there are few inspection points are
unattended and made available for further inspection . how is this mapped . can some one help me in this regard.
thanks
ksr
Hi
This is only possible by making all of the characteristics as "Long term" in control indicator.
After UD status will change to "LTIN"
this will allow you to do Result recording & defect recording at later stages also
Regards
Sujit