We are using quality certificate and using TX QC51 to receive certificate before doing Good receipt.

What we want to do is, if the certifcate is not received we want to receive the stock in blocked stock.

I noticed there is a config for certificate key where by it says "without lot, blocked stock; with lot, error message"

Can we receive a material into blocked stock if certificate is not received ? or it can only be done if Inspection type is not active.

Pls advise.

Thx

Gaurav

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Can we receive a material into blocked stock if certificate is not received ? or it can only be done if Inspection type is not active?

Yes this is very much possible provided that you click on "Certificate check req" in the type of certificate that you are using.

then select :Without lot :block stock,with lot :status

here status means "CTCM:certificate confirmation req" during UD

but this will only work when you do not have inspection type active as you said.

so what you can do is put warning or error instead.

I hope you understood