on 09-10-2009 2:34 PM
Hi Experts,
can anybody explain in which scenario we go for PS n CS integration...and
what are the broad level steps for integration...
thanx in adv.
regards
ashis
Hi Ashish,
You can create Service Order using oreder type SM01 in PM. In that PM order on additional data tab you can assign a WBS from PS. All the service/work will carried out from Service Order, while the WBS will be used for cost collection.
Thanks
Sarang