on 09-09-2009 10:52 AM
Dear All,
I have this situation where when I do the confirmation for activity elements within an activity, due to a fractional progress, the values for Actual POC percentage are coming too small. For example the Work for an activity element is 100000 m3 and while confirmation, i enter actual work as 150 m3, the POC comes as (150/100000 * 100 = 0.15%).
In this case when I run CNE5, system gives a warning as "You have selected different units for calculation the work and the duration.
In this case, the calculated value of work would be very small. Since the field only allows one position after the period, the system represents this value with 0.0. However, this would be misleading because there actually is work"
Due to this, the system is not rolling up the POC actual aggregate to the top.
Please help.
Regards,
VikasD
Hi,
Go to Tcode: OPTU
Select : SAPPS_EV0001 or as per your selection criteria.
The last column has Decimals. Please mention the number of decimals you would like to see.
Hope it helps...
Thanks!!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.