Dear Gurus,
I am sending the PIR's to APO. Should i also tick Req.Reduction in CFM1? or it's optional
Prasanna
The problem is solved by adding the Category EQ in the category group ZVS. This will reduce PIR in APO when the PGI is done for STO delivery. The path for this customizing is
SPRO>APO>SCP>SNP>Basic setting-->Maintian category group
Prasanna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prasanna,
Could you just provide the inconsistency error that you
are facing?
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
the reason for asking is , i am always getting inconsistency in PIR data between R/3 and APO. will it get solved if i activate that in CFM1,becos currently it's not activated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Prasanna,
In your business scenario, if there is any requirement reduction exists, then you need
to create separate integration model to address that event and to update that data.
If this event does not exist for your scenario, separate model for requirement
reduction need not to be selected.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Prasanna,
While transferring the PIRs from R/3 to APO it is not mandatory to select the option of 'Req reduction' in CFM1.
The use of this indicator is to control the selection of product-location cobinations for which the Requirement Reduction should take place.
That is if you do not select this indicator, the requirement reduction would be transferred for all material-location combinations for which an active integration model exists.
If you set this indicator, you can create separate integration models for Requirement Reduction and in the filter criteria specify the materials and locations for which you desire the requirements reduction to be transferred.
Thus it is not mandatory to check the option 'Req. Reduction' for successful transfer of PIRs.
Hope this clarifies your doubt.
Regards,
SCMLearner
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.