Hi Experts,

I am doing cost planning and Budgeting in IM35 and IM32 and surprised to see that in both the caes even though the overall values are less that the annual values then also the system is allowing me to save but if i check the values before saving by the check button i am getting the error message as desired.

I want to know - is it the standard behaviour of the system?

One more problem is on the IM plannig vesions, when i created the version, i have assigned it to the current fiscal year and controlling area and checked the setting as locked and copying possible. Buit when i open the version in IM35, then the system allows to do the changes to the plan values of the version.

Request you to share your experiance please.

Thanks

Accepted Solutions (0)

Answers (1)

Answers (1)

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Please refer the Note: 398983

Hope it helps...