on 09-08-2009 9:25 AM
In this scenerio PS budget management is in use long back for WBS budget check.
Now FI team activated fund management for OPEX part and place DUMMY commitment item for WBS (for transaction other than 30).
Now in this case for service order which alredy created almost year back and almost all service entries are happened.
now user is trying to close this service order by changeing service quantity in PO equal to actual service.
i.e in PO 600005964 for Service 8000125 PO qty is 100 and actual service entry happened is 95. now user is changeing the qty in po from 100 to 95 to clost the PO.
while doing this system is giving budget exceed error for a/c assigned WBS.
When WBS was having extra budget other than commitment user had done some changes and that time system created exta a/c assignment in that PO as DUMMY in table extra ESKL DUMMY commitment item is created for this PO
For trial and error we temporary deactivated Fund management and tried to change the qty this PO at this time system is not giveing any error message and i can change the PO qty from 100 to 95 w/o any error.
Can anyone plese tell me how to tackle this issue because fund management is required for OPEX part and we cant deactivate it. by keeping fund management activated how resolve this issue for WBS.
Hi,
Not sure which release you are working on.
But please check the note 371069..
Hope it helps...
Thanks!!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
i think this error is coming because of Fund management.
When ever any actual posting happens, if the availability control is activated in Fund management and Budget profile in project,
Then system will check available budget at both the place.
For you scenario:
soln-1 deactivate the availability control in Fund management
soln-2 assign fund center with wbs element and supplement budget = actual cost of 95 qty in FM.
ashis
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Please check in Budget Tolerance if you have maintained any other Availability Control Activity Group other than "++". Because this additional Tolerance control will superceed the control set with ++.
Hope it helps.
Regards
Babu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
11 | |
10 | |
6 | |
5 | |
5 | |
5 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.