Material Assignment in Inspection Plan

Former Member
0 Kudos

Dear All,

what is the maximum number of material that we can assign, to an inspection plan by Mat-TList assignment?

I thought of let users to assign materials by task list assignment by this way because for all the material inspections, there will be same MIC. what are the implication of doing this?

Regards,

DTD

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You can assign as many material assignments as you want,i have once assigned 7000 materials.

There will not be any implications it will be useful in case there are common specifications for all the materials.

CSN

Former Member
0 Kudos

Hi

DId u assign all 7000 material in one inspection plan and counter or different countes

did u create this as one data load.

Because we have same requirement allmost 4000materials inspection characteristic and specification are same.

I am thinking to create one inspection plan group and counter.

Is't possible to do by BDC....

thanks

Sami

Former Member
0 Kudos

Hi,

I have assigned all 7000 materials to one inspection plan and single group counter.

We can do the material assignment through BDC.But i dont have the code for BDC .

Regards

Sreenath