on 09-05-2009 5:23 AM
Hi all,
While creating a sales order, system is creating schedule lines after two days of order creation. I want that schedule lines should be created for the same date.
Please suggest that what should I do for this?
Please respond.
Best Regards,
AI.
Resolved myself. server date is not correct.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
check whether any delivery scheduling is been maintained
IMG>SALES AND DISTRIBUTION>BASIC FUNCTION>DELIVERY SCHEDULING AND TRANSPORTATION SCHEDULING>MAINTAIN DURATION
choose shipping point and remove the "Loading time w.days" and "Pick/pack time wrkdys" if maintained any
choose route and remove "transit lead time"
now try with new sales order
regards
senya
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
See whether the material have been locked in any other order. through t_code V_RA. If it is confirm the quantity for needed order.
Regards
RaJ
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Go to IMG u2013 Enterprise Structure u2013 Definition u2013 Logistics Executive u2013 Define, copy, delete, check shipping point.
in this check whether any pick pack time or loading time is given or not.
If given then remove it and save it.
Now go to 0VTC and select your route from this.
Check the transtidur and transldtm setting.
Whether any setting is saved over here for these then remove it and save it.
Now check in your sales order by creating it whether every thing is right or not.
Regards
Raj.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check your material Master in MRP2 View > In-house production.Here you have mentioned 2 days.
Best Regards,
Ankur
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Along with the suggestion of venky, Please maintain the Lead time as 0 in VOV8 for your sales document type.
Thanks,
Raja
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Maintain Replinishment lead time as 0.in material master.
Regards
raj.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.