Hi!

Everytime we create PRs in PS, and we convert the PR to PO, the PO gets the network number of the PR and the account assignment becomes N(network). Is it possible that instead of network, it gets the WBS and the account assignment will be P(project)?

Thanks!

Paula

Accepted Solutions (1)

Accepted Solutions (1)

former_member203108
Active Contributor
0 Kudos

This message was moderated.

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

The acc.assignment to the network activity, from where you created the PR, is standard and makes sense. To get it linked to a WBS I guess you have to create the PO manually in MM, or you have to to use some very sophiticated solution where you use a projects stock.