on 09-04-2009 3:52 PM
Hello All,
Can you tell me of any Transaction or Program that will help me in doing the rescheduling or the back order processing.
Basically need to confirm sales order stock automatically when the stock is received.
Any inputs on this process will be appreciated.
Thanks
SAP Fans...
Have you come across V_V2 or co06 ??
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Yes I know this Transaction but need more information of how it works.
Also there are not many input options(like customer,etc) within this transaction. Is there any exits with this backorder program where we can customzie the working of it. We only have Plant and Material as input.
Please throw some light on how to use this Transaction.
Thanks
SAP Fans...
Hi,
V_V2, V_RA
Ahmed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
V_V2 as std will be done based on the materail at plant level .If you want customet in the selction screen you need to copy the std program of V_V2 to ZV_V2 and the requiremnt of customer or any otehr selction parameters.As std backodering can be doen at Materail at plant level.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.