cancel
Showing results for 
Search instead for 
Did you mean: 

MC8T - Define Activities for Mass Processing

Former Member
0 Kudos

hi!

We are in the process of upgrading from APO 3.10 to SCM 5.0.

We have noticed that /SAPAPO/MC8T - Define Activities for Mass Processing, which was present as a configuration node under SPRO > SAP Advanced Planner and Optimizer (SAP APO) > Supply Chain Planning > Demand Planning > Mass Processing in APO 3.10 is no longer listed under SPRO in SCM 5.0.

We can still access it directly by using the t-code.

Is it by design that the node has been done away with in SCM 5.0 ?

regards,

Anirudha

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Anirudha,

Yes there is couple a change between 3.1 and 5...

This transaciton is not accessable from the SPRO, but is in the main "SAP easy access"

Advanced Planning and Optimization > Demand Planning > Planning > Demand Planning in the Background

/SAPAPO/MC8T - Define Activities for Mass Processing

The the node is not away, stil there and still working.

Thanks and Regards

Julien

Former Member
0 Kudos

Thanks,Julien.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi Anirudha,

SAP has relocated MC8T from spro to transactional path from scm 3.1 to 5

is to ease for operational purposes, to indicate users that this is an

transactional operation and not a configurational activity and also to

group the activities under demand planning.

Regards

R. Senthil Mareeswaran.

Former Member
0 Kudos

Thanks, Senthil.