on 09-04-2009 10:39 AM
Hello All !
We would like to set up the cartography system in our Warehouse Management.
I know that SAP has a cartography module integrated and based on a "geoconcept" strategy.
But I don't know if we must to configure an interface or add a new component. Is there only customizing ?
Thanks for your feed-back,
Sandrine
Hi,
You can also check the SAP material "SCM635 - Task and Resource Management" for more information on resource management.
Regards,
K.Annadurai.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
What SAP version are you on? You can use TRM to optimize your WH - this is std functionality in ECC - up to a certian point, but with SCM EWM you get more advanced functionality.
Regards,
Hein
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
By "cartography", do you mean 3D models of the warehouse? I don't think SAP has such a module.
Can you please share the information you have on this?
Regards,
Osman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Osman,
We would like to optimize the physical goods movements.
Today, we have some people in reception, shipping, picking etc. The idea is to say that if a Fork-lift truck driver moves a pallet in a storage bin in the stock then the system checks if an transfer order is opened,for example a reorder transfer order.
Therefore the Fork-lift truck drivers will process differents transfers orders in the Warehouse.
I don't know if this concerns the 3D models but we found some informations on this functionality ...
Thanks,
Sandrine
Hi Christian
Based on the information . what i understood is
you are having few MHE (Material handling equipment) and you want to utilize the resource effectively to get maximum Output.
Also if any open transfer order exist for the storage bin then system should not allow the MHE to travel to those bin location (This is the standard functionality of SAP if any open transfer order exist then system won't allow the second transfer order for the same bin(depend on the config).
Please confirm whether my understanding is right or please explain your requirement in detail so that we can help you.
Regards
Manish kumar
Hello,
My understanding of your scenario is follows.
When forklift driver moves material to bin for placement & he comes to know there is picking transfer order created in the system. To avoid the forklift to move empty ,driver shall pick up material from returning to ship the same.
For this you can use RF queue in which TO's are assigned to user queue. You have to configure mobile data entry functionality to use interleaving transaction. In interleaving system automatically prompt user to pick material (TO) after the putaway activity (TO) completion.
Let me know your whether this is you looking for.
Regards,
Prashant
Hi !
Thanks all for your feedback !
Prashant,
that's right ! : The objective is to avoid the forklift driver to move empty, we would like to optimize their moves.
Today we use the RF queues (LRF1) and we assign (manually) the users to the queue according their job. But we would like that the system assign automatically a TO to a forklift driver according her location in the Warehouse, then the queue will change automatically. (When a TO is created, it is assigned automatically to a queue according the return storage type).
Sorry but I didn't understand the next step, what did you mean by " You have to configure mobile data entry functionality to use interleaving transaction" ?
Best regards,
Sandrine
Hello,
1.As per my understanding TO's can be trasferred from one queue to other queue by LRF1. I do not know whether it is possible to assign automatically depending on the user location. I believe supervisor contols that.
2.Sorry but I didn't understand the next step, what did you mean by " You have to configure mobile data entry functionality to use interleaving transaction" ?
I mean to say that you have to do Rf config. i.e menu mgt. RF queues etc. From your answers I assume that you have done Rf configuration . You just have to add interleaving transaction in your menu mgt.
Please let me know if any query,
Regards,
Prashant