Hi experts,
I have a Integration Process it takes two files one Header xml and one Lines xml. These files shoudl be processed at the same time because them will be mappend in a Idoc.
The realy trouble is that these inbound xmls never are executed at the same time. Then a IP is executed for each inbound xml.
This is the IP:
http://picasaweb.google.com/hose86/SapXi#5377539387476591346
This is related documentation:
http://help.sap.com/saphelp_nwpi71/helpdata/en/cb/15163ff8519a06e10000000a114084/frameset.htm
I try to do all what I know, but It don't work fine :S
Thanks in advance and Regards,
Jose Antonio.
Hi Jose,
Don't specify any end condition for fork step and check the start process check box in both the receive step.
Also put all steps inside the block.. so that the control step in deadline branch can throw exception and after that the BPM ends. As per the design now, if a deadline exception is raised (it will b handled) but after that the transformation step and send step is executed. There the BPM fails.
Regards
Suraj
Edited by: S.R.Suraj on Sep 4, 2009 5:39 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
90 | |
10 | |
10 | |
10 | |
7 | |
7 | |
6 | |
5 | |
4 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.