on 09-03-2009 10:27 PM
Hi All
This is the CIF error "Material status does not allow a planned independent requirement"
Any suggestions?
Thanks
Pooja
You might want to check the MRP1 view if it has a block, like blocked for purchasing or for all activity.If there is any, removing it, should solve the issue.Of course as stated in the previous post, Basic 1 blockage is a possibility.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Pooja,
Can you please check in your R/3 system for the material and plant whether you have specified any value for the field
"X-plant matl status" in the Basic data 1 tab. If yes, check whether the customizing for this value is flagged for the field
"Ind. reqmt msg" with value "B" in the following path:
SPRO > Logistics - General > Material Master >
Settings for Key Fields > Define Material Statuses
Make this value blank and check it again.
You can use the UserExit EXIT_SAPLCMAT_001 to filter based on the material status. Please also refer the following notes:
964360 APO PP/DS: Material status II
331664 APO PP/DS: Material status
357955 Transfer material status f.check d. pl. order conv.
I hope this helps.
Regards,
Tibor
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pooja,
Please check on the following:-
1) plant-specific material status in MRP1 view of R/3
2) MRP3 view :- dependent requirement fields whether maintained properly
3) Forecasting views whether maintained correctly.
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
6 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.