on 09-03-2009 7:00 AM
Hi,
I have one requirement regarding the shipment cost document.
Generally, shipment cost document will determine the system data as settlement date. Now my requirement is shipment cost document to determine the PGI date.
Can anybody throw some light in this requirement how to procced.
hello, friend.
i think you can define your own settlement date determination rule by going to T_60. you can specify a sequence for a date (e.g. start date for stage) which will approximate your goods issue date.
after this, you assign the settlement rule to the shipment cost item category in T_56.
hope this helps.
regards.
regards.