Define tolerance limits - Budget

Former Member
0 Kudos

Hi

In Define tolerance limit for Budget, which activity group should i remove, for remaining order plan to get excluded from budget availability control.

Thanks in advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

You can try removing the planning indicator in OPSC so that assigned values do not get appended from the network plan costs.

Regards

Srikrishna

Answers (1)

Answers (1)

virendra_pal
Active Contributor
0 Kudos

remianing order plan are orde commitments

try group 02

however these will not exclude networks