Hi
In Define tolerance limit for Budget, which activity group should i remove, for remaining order plan to get excluded from budget availability control.
Thanks in advance
Hi
You can try removing the planning indicator in OPSC so that assigned values do not get appended from the network plan costs.
Regards
Srikrishna
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
remianing order plan are orde commitments
try group 02
however these will not exclude networks