Hi Team,

Pls suggest me "How to assign sampling procedure at plant level."

Error message is - You can not use sampling procedure here.

Not all sampling procedures can be used in this context.

Example:

Only the sampling procedures for an attributive inspection based on the

number of nonconforming units are allowed.

However I have assigned 0.05% sampling procedure in IDES system plant, which is accepted. However I am not allowed to assign this in client system..

Pls suggest me solution.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

are you applying sampling procedure at "Inspection lot creation" tab in Lot inspection at plant level.

can you please more elaborate sampling procedure.

since you can not use Inspection point.

you can not use without valuation.

Regards

Sujit

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

During creation of inspection plan you can assign SP at plant level, IP always at plant level

Q.Error message is - You can not use sampling procedure here.

---> pl check the MIC where Sampling procedure in clicked or not

pl revert

Cheers,

Former Member
0 Kudos

if u are applying this sampling procedure in inspection plan qp01 then check whether inspection characteristics is qualitative or quantitative.

if it is qualitative then sampling procedures for an attributive inspection based on the number of nonconforming units will be allowed.

also check in sampling procedure 0.05% what is valuation type in ides system and production system.