on 09-01-2009 4:11 PM
Hi,
If i Use Production Supply area and Control cycle SAP allow me to replenish stock Material by Material?? Is there any other transaction where i can do replenishment for materials collectively??
Regards
Shrinivas
Hi Shrinivas,
Plz make the question clear. You want to create control cycles (Master data) collectively? or staging collectively?
If you want to stage collectively, you can use MF60. Also tell us how you are now replenishing stock Material by Material??
Regards
It also depemds on your Control cycle. You have to use your Staging ind. 3 (Rel.ord.part)
Edited by: Nageshwar Rao on Oct 27, 2009 11:49 PM