Plz give me configuration steps for MRP

Accepted Solutions (1)

Accepted Solutions (1)

Former Member

Hi,

Following steps need to be follow for configuring MRP

1. Plant Parameters for MRP (SPRO)

2. MRP type (MM)

3. MRP controller (MM)

4. Procurement Type(MM)

5. Special Procurement Type if applicable (MM)

6. Lot Sizing Procedure (MM)

7. Scheduling Margin Key(MM)

8. Scheduling Parameters for planned orders through (SPRO)

Detail:

1. Activate Plant Parameters for MRP(in SPRO)

2. MRP Type Customization(E.g, PD, M1,M2,, -in SPRO - But need not suposed to do without client's permission)

3. MRP Controller (in SPRO)

4. Production Scheduler Profile (in SPRO)

5. Order type Dependent Paremeters(in SPRO)

6. Plant Parematers(in SPRO)

7. Scheduling Parameters(in SPRO)

Important T-Codes - OPL8,OPJH,OPKP

Note: Go to SPRO, select reference IMG,

Select Production - Material Requirements Planning, Here you will get all the details about the setting for MRP

by

Prabhu

Answers (4)

Answers (4)

former_member184655
Active Contributor
0 Kudos

Dear Prasad,

Front End settings:

1.MRP type,MRP controller,Planned delivery time(for externally procured items),In-house production time(for inhouse

manufactured products),Floats (Scheduling margin key),Lot size indicator,factory calendar if used,Planning strategy,BOM

selection method.

All these settings to ne made in MRP1,2,3,4 views of the material master.

SPRO settings,

1.In OPPQ plant parameters for carrying out planning run.

2.In OPPR for the MRP group parameters.

3.Activate MRP areas if used any

4.Activate MRP for plant,Planning file entries (OMDU and MDRE) - you can check by branching this menu->SPRO->production-

-->MRP --->master data.

5.if you want to use MRP area check this link,

MRP Area

Main MRP settings

Steps for carrying out MRP for multiple plant

Regards

Mangalraj.S

Former Member
0 Kudos

HI

Gurus, I am having MRP presentation at ICE cream manufacturing factory on Monday. Can you Pl help me to prepare the presentation, mainly the advantages of MRP implementation, I have to convince my client to implement MRP, at present they r all doing manually in Excel. They might thing itu2019s a extra work for them, also guide the client side questionnaire and the pres steps to implement MRP in the factory. It would be so helpful if u reply. Thanks for ur efforts and time

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Please refer this link,

[MRP Configuration|http://www.sap-topjobs.com/SpecialPP/overviewdoc.pdf]

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi Prasad,

At first u need to activate MRP in the below path:

Spro-MM-Consumption-Based PlanningPlanningActivate Material Requirements Planning

Later Maintain the material with all 4 views of MRP.

Steps with Demand Mgmt Sequence ) MC87

MC78

MC74

MD04

MD02

Steps withOUT Demand Mgmt Sequence )

MD61

MD04

MD02

Regards