What is the impact of changing the CC of a WBSE when the original CC is still holding some value of the WBS?
Just by changing the CC will not transfer values. So my question is how can we go about it so that the new CC receives the original values from the old CC.
In a way i want to know how can we implement the intra company asset transfer (changing CC) scenario in the case of WBSE.
Before you change the cost center....ensure that you have transferred all cost from the exisitng cost center to the new cost center. use transaction KB61 or create a distribution cycle.