Hi,
Basically CN41 report shows object wise cost/revenue/commitment/budget for one or more number of projects. Is it possible to show the SAP Standard Report CN41 with excluding some cost against any object (WBSE/Activity/Activity Element). Thats is it might be excluding the cost incurred on some specific cost elements. I can achieve it with cost element report but can it be done with CN41/CN41N report ?
Or
Any Standard cost elements report with Cost/ Revenue/ Commitment details where i can exclude perticular cost elements ??
Is there any parameters we can set in DP profile/Selection profile. But this requirement should be available only for a specific user Ids not for all users.
Thanks & Regards,
Hari Krishna.K
maybe T-Code s_alr_87013543 or cji3 helps.
try doing.
rgds
Edited by: robert lion on Aug 31, 2009 10:06 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
use value category to do this
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.