08-31-2009 8:26 AM
Dear All,
Client requirement in my project is billing should be done every month 15th . If we will give 15 days in portin it will create schedule records in 15 days gap and it is not exactly 15th of every month. So I am giving one month in portion and doing interim billing on 15th of every month.
Apart from this is there any other enhancements to create scheduled records or any other option to do this. Please write it clearly.
With regards,
Rohit
Edited by: Ramrohit on Aug 31, 2009 9:27 AM
09-08-2009 4:56 AM
Hi,
Not sure if you have explored the option of "Alternate Portion" at the contract level. SAP provides BADI ISU_BFPS_APIV for defining user-defined checks for Alternate Portion.
I dont think there are any user exits/BAdis for schedule creation/updation.
Thanks,
Sai