on 08-28-2009 11:28 AM
Dear All
How to use material BOM in PS. what are the setting required for it.
Please give me the valuable solution to me
Regards
Raj
Dear,
create WBS bom cs71, assign reference points to sub items and use same reference point to activity in assignment tab.
then transfer bom (cn33) and in transfer control define project definetion,header material,reference point,and wbs
element.
Result> material assigned to activities and order reservation is created.
then run MRP(MD51) > dependent requirement will create.
PR>PO>GRN>GI for sub material9mov type 281)
Confrmation of activity and GRN for header material is automatic GRN then tick Backflush indicator in material in
procrument tab of material.Material come to stock and actual cost will come.
Regards.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
BOM Usage
This key defines the area (such as engineering/design or production)
where a BOM can be used.
Use
By setting various indicators, you can define the maximum configuration
of the item status and define whether an item must be or cannot be
processed in a particular area (such as production).
Examples
A material is used in the areas production and costing in a company. For
each area, you maintain a separate BOM with different items:
o Production BOM:
This BOM contains items that are relevant to production. These items
Costing BOM:
This BOM contains items that are relevant to determining the
material costs of a product.
When you calculate production costs using a quantity structure, the
system automatically determines the BOM and all the BOM items that
are relevant to costing, in order to calculate manufacturing costs.
As i've told you that quantity is negative coz you have to produce that material or the header material should come to stock as the rasult of MRP run and it should GRn and come to stock.
Regards.
Hi
Define Profile for Bill Of Material Transfer with BOM option as material BOM (path -> SPRO -> PS -> material -> BOM Transfer -> Profile for BOM transfer). Maintain the other settings like BOM Application, Usage, transfer parameters and constraints as per your requirement.
Now create a Material BOM in CS01 and assign this material to Network activity with required Qty. Now goto BOM transfer (CN33) Transaction and select the BOM transfer profile and transfer child items w.r.t requirement qty to PS.
Hope this helps you !
Br
Hari.
Edited by: Hari Krishna Kudaravalli on Aug 28, 2009 4:05 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.