on 08-28-2009 10:52 AM
Hi Experts,
I changes SAP Script and assigned to Transport request. After release TR to quality, but changes was not appear in quality. Package is correct and working fine in dev. Transport request log was also Successfully imported. Every thing is fine but changes was not there in SAp Script Main window? In QA, sap script showing changed date was TR importing date.
Any body please give the cause of this issue.
Thanks in Advance,
Siva
i solved myself
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Try This......
Go to Quality server enter T-Code SCC1 in that enter the client where you made changes to SAP Script
and Trasport Request and check the box "Including Request Subtasks" and then click on "start Immediately" Button
then go and check the script you will find your changes in quality..
Thanks,
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Siva,
Make sure with your basis consultant the TR has been successfully imported to QA system.
Rgds,
Sripal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
10 | |
9 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.