Restrict the activity release before the WBS release

Former Member
0 Kudos

Hi Expert.

Today, the use can release activities even the related WBS is not release. is that possible to restict the activity release before WBS release.

BR, Shubin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

I am not sure if you can achieve this by standard config setting. However, you can try exit "CNEX0028 = Check activity release".

Collect PROJN and fetch OBJNR of the WBSE from PRPS table. Pass OBJNR and status = I0002 (REL) in to Status_Check Function module. Accordingly if WBS released then allow activity release. Else forbid.

Thanks

Saikishore.Ganga

Former Member
0 Kudos

Hi Saikishore.

Thanks a lot !

BR, Shubin

Former Member
0 Kudos

Hi Saikishore

Would you tell me the table of WBS status ?

Thanks and Regards

Shubin