Hi Expert.
Today, the use can release activities even the related WBS is not release. is that possible to restict the activity release before WBS release.
BR, Shubin
Hi,
I am not sure if you can achieve this by standard config setting. However, you can try exit "CNEX0028 = Check activity release".
Collect PROJN and fetch OBJNR of the WBSE from PRPS table. Pass OBJNR and status = I0002 (REL) in to Status_Check Function module. Accordingly if WBS released then allow activity release. Else forbid.
Thanks
Saikishore.Ganga