What is the purpose of the Dates tab on the Outbound Delivery header? What are the events that may be added and can we add our own?
This tab is not available on the Inbound Delivery. Why is that?
Thank you,
>> What is the purpose of the Dates tab on the Outbound Delivery header?
Well, to check the correct planning of the delivery from a time perspective, usually based on Requested Delivery Date at the customer site: Material availability date, Transportation Planning date, Loading date, Goods Issue date.
>> What are the events that may be added and can we add our own?
These dates are automatically calculated based on customizing and master data.
>> This tab is not available on the Inbound Delivery. Why is that?
Maybe because there is not the same need for scheduling for an inbound delivery than for an outbound delivery.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.