Just want to check whether operation can be added into lot manually? Due to cutomer need.
hi
No opration dynamically can not be added in a task list/routing used in inspection type 03.
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I think so. The problem I met is the customer cannot confirm their routing before release order. They released order first then complemented the operation gradually. So this made the problem, the insp. lot cannot update automatically unless I read PP master data again, but if one operation was confirmed then the Pro. order cannot be read. So how the operations which were added after release order are added into insp. lot?
Thanks
I think you can't add operation but you may add MIC during RR.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
91 | |
7 | |
7 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.