on 08-27-2009 10:06 AM
i set over-dilivery in PO, the real good received amount is beyond the WBS budget, but i found it could finish good receiving without any error message, it seems that the budget is out of control in MIGO. is anyone could tell me the reason? thanks!
If your availability control settings are appropriate then chekc this note.
46209 No availability control for goods receipts
755495 Allow Availability Control for Goods Receipts
324486 Availability control for goods receipt MIGO
With Regards
Nitin P.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
The reasons could be
(1) Budget mihght not have been activated. Check in WBS System Status AVAC is there. If not, run CJBV with your Project No.
or
(2) In SPRO - In Budget Tolearance you might not have maintained "++" or "03" in Activity Groups against your Budget Profile.
Hope it helps.
Regards
Babu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.