ECP on Network Activities

Former Member
0 Kudos

Hello PS Experts,

We are on ECC6 Enhancement Pack 4 client.

The issue is that the Network Activities do not appear on the Easy Cost Planning screen for planning.

I can only see the WBS element structure, similar to the old functionality.

(To my understanding this new functionality is available since ECC6 EhP 3).

I believe, the only configuration required for this is as below and is done.

Project System >Costs>Planned Costs> Easy Cost Planning and Execution Services >Easy Cost Planning>Activate Planning for Network Activities with Easy Cost Planning

Any inputs on why it is not working ?

Thanks in advance.

Bhushan

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

have you tried transaction CJ9ECP?

The only thing I can think of right now is that the network type may have to have planning ticked

Former Member
0 Kudos

Thank you for the response.

I checked with CJ9ECP. But no luck. Same result.

Planning is ticked in the config for the Network Type (PS01) as well.

Former Member
0 Kudos

Thank you for the response.

I checked with CJ9ECP. But no luck. Same result.

Planning is ticked in the config for the Network Type (PS01) as well.

virendra_pal
Active Contributor
0 Kudos

i think you need to activate multiple co version for ECP

Former Member
0 Kudos

Hi Virendra,

I did that as well. But still no luck.

Former Member
0 Kudos

It is working now.

Multi-CO Version needs to be activicated for the respective CO area and in the 'Edit Costing' window, that pops-up, one should click on the 'Edit' button before the first time save.