PoC revenues and costs are 0

Former Member
0 Kudos

Hello,

I have PoC , planned revenus & costs values entered, actual costs but no actual revenues for the project. I run tran CNE1 , CJB2, KKA2, CJ88 to get Result Analysis (PoC revenues and costs).

But they are 0.

How to get aPoC revenues and costs?

Accepted Solutions (1)

Accepted Solutions (1)

virendra_pal
Active Contributor
0 Kudos

you need to configure RA

RA calculates PoC

If you are entering PoC and running CNE1 - these are tranaction for Progress Analysis

I think you are having some confusion between Results Analysis and Progress Analysis - these are two distinct functionalities and can be used in tandem.

Answers (1)

Answers (1)

former_member203108
Active Contributor
0 Kudos

This message was moderated.