Dear All,

I need to implement PS in R&D.They need mateial some produce in house some prucore from out side.

I have made WBS&Activities and reference point is assigned to activitieds.

WBS bom is creted and assign two raw material to theat BOM.

After bom is transfered by cn33 header material is assigned to activity A and other sub material is assigned to activity B

After MD51 planned order created for material assigned to activity B.And PR>PO>GRN>GI is done for activity.

But for header material in activity A has order reservation and movement type 581.IT has to come to stock.

How can i GRN for header material in Activity A,it have procrument type X.

IF i am doing any wrong process then tell me the proper solution for R&D.Need valuable feedbacks.

Regards.

Edited by: Sukhveer Singh on Aug 26, 2009 11:48 AM

Edited by: Sukhveer Singh on Aug 26, 2009 2:08 PM

Edited by: Sukhveer Singh on Aug 27, 2009 6:20 AM

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Dear,

Its movement tpye is 581(header material) and after confermation of activity A also its not comming in stock in MD04.

If its needed that i confirm the activity A after issuence of sub material?

What is the steps i m missing ?

Edited by: Sukhveer Singh on Aug 28, 2009 6:42 AM

Former Member
0 Kudos

Hi,

Black Flush Indicator must be falgged. Please verify. Check Accounting view for the material in specific plant and storage location must have been defined.

GO to T-code COGI and give WBSE , material , Plant Storage Location. Error records for automatic Goods movement corresponding to the same will be saved.

Correct the error, select the row in COGI and save. Goods movement will be posted.

Thanks

Saikishore.Ganga

Former Member
0 Kudos

Hi,

Black Flush Indicator must be falgged. Please verify. Check Accounting view for the material in specific plant and storage location must have been defined.

GO to T-code COGI and give WBSE , material , Plant Storage Location. Error records for automatic Goods movement corresponding to the same will be saved.

Correct the error, select the row in COGI and save. Goods movement will be posted.

Thanks

Saikishore.Ganga

Former Member
0 Kudos

Dear,

ITs the problem of MM period.

Now its working fine.

Thanks.

Former Member
0 Kudos

Dear,

Its working but after posted from cogi also its not showing its actual value.

Its comming to stock but actual value is not comming .

How its actual value will come against the WBS element?

Or it will come for sub items when issued to activities.

Regards.

Edited by: Sukhveer Singh on Aug 31, 2009 6:31 AM

Former Member
0 Kudos

This message was moderated.

Former Member
0 Kudos

Dear,

I just want to know when materials actual cost will come?

After it comes to stock or i have to issue it again against reservation?

Regards.

former_member203108
Active Contributor
0 Kudos

This message was moderated.

Former Member
0 Kudos

'Thanks Dear,

Now its working fine after GRN its actual is comming.

Regards.

Answers (2)

Answers (2)

Former Member
0 Kudos

Answred

Former Member
0 Kudos

still not answered