Dear All,
I need to implement PS in R&D.They need mateial some produce in house some prucore from out side.
I have made WBS&Activities and reference point is assigned to activitieds.
WBS bom is creted and assign two raw material to theat BOM.
After bom is transfered by cn33 header material is assigned to activity A and other sub material is assigned to activity B
After MD51 planned order created for material assigned to activity B.And PR>PO>GRN>GI is done for activity.
But for header material in activity A has order reservation and movement type 581.IT has to come to stock.
How can i GRN for header material in Activity A,it have procrument type X.
IF i am doing any wrong process then tell me the proper solution for R&D.Need valuable feedbacks.
Regards.
Edited by: Sukhveer Singh on Aug 26, 2009 11:48 AM
Edited by: Sukhveer Singh on Aug 26, 2009 2:08 PM
Edited by: Sukhveer Singh on Aug 27, 2009 6:20 AM
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Black Flush Indicator must be falgged. Please verify. Check Accounting view for the material in specific plant and storage location must have been defined.
GO to T-code COGI and give WBSE , material , Plant Storage Location. Error records for automatic Goods movement corresponding to the same will be saved.
Correct the error, select the row in COGI and save. Goods movement will be posted.
Thanks
Saikishore.Ganga
Hi,
Black Flush Indicator must be falgged. Please verify. Check Accounting view for the material in specific plant and storage location must have been defined.
GO to T-code COGI and give WBSE , material , Plant Storage Location. Error records for automatic Goods movement corresponding to the same will be saved.
Correct the error, select the row in COGI and save. Goods movement will be posted.
Thanks
Saikishore.Ganga
Dear,
Its working but after posted from cogi also its not showing its actual value.
Its comming to stock but actual value is not comming .
How its actual value will come against the WBS element?
Or it will come for sub items when issued to activities.
Regards.
Edited by: Sukhveer Singh on Aug 31, 2009 6:31 AM
Answred
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
still not answered
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.