Hi all.
I have a question. When I create PO from SC, I found I can create several POs, even if the SC already ordered.
E.g:
The SC:1000000011 has 1 item, the Qty is 10. I create a PO: 7000000005 with whole Qty 10.
And then, I can also create another POs, which reference to SC:1000000011.
So, I want to know how to control the PO, if the SC has already ordered.
PS: I have set the message "BBP_PD 778: Complete quantity of shopping cart &1/&2 already ordered" to E, but it unusable.
Johnson
Hi,
Kindly review and fully implement the following notes:
1168632: BBP_POC: Shopping cart status not updated properly
1066794: PO deleted from a Bid sends the related SHP item to SOCO.
Please ensure these notes are completely implemented and then retest the systems behaviour.
I hope this helps,
Kind Regards,
Lisa
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi johnson
Can you explain in detail how you are ordering PO w.r.t SC.
for sc created 10 qty if fixed source of supply it created PO for 10 qty immediatelyright.
how do you reorder a cart. once cart is ordered and follow on document created it is no more editable right
br
muthu