on 08-25-2009 11:55 AM
Dear All,
I am using valuated stock scenario. I am creating production orders which are account assigned to grouping WBS elements. In OPSV, I have mark the indicator "addition" so that order cost is updated at WBS planned costs.
I have two problems here:
1) Cost is not getting appended to WBS element for production orders which are converted from MRP planned orders.While for manual production order, it does append the cost to WBS element.
2) The planned costs for production orders created from MRP planned order does not show the total planned cost i.e. it shows only labor costs but not material costs. While in case of manually created production orders it does show the complete planned costs i.e. material and labor both.
I am using version 4.7 for this scenario. Does anybody has same experince in the past.
Thanks in advance !
Regards,
Mahendra Dighe
PS Consultant, Pune, India
hi
check the customization settting in the value category and cost element assigned to the vlaue category.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.