Porduction Order planned costs in project reports

Former Member
0 Kudos

Dear All,

I am using valuated stock scenario. I am creating production orders which are account assigned to grouping WBS elements. In OPSV, I have mark the indicator "addition" so that order cost is updated at WBS planned costs.

I have two problems here:

1) Cost is not getting appended to WBS element for production orders which are converted from MRP planned orders.While for manual production order, it does append the cost to WBS element.

2) The planned costs for production orders created from MRP planned order does not show the total planned cost i.e. it shows only labor costs but not material costs. While in case of manually created production orders it does show the complete planned costs i.e. material and labor both.

I am using version 4.7 for this scenario. Does anybody has same experince in the past.

Thanks in advance !

Regards,

Mahendra Dighe

PS Consultant, Pune, India

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

check the customization settting in the value category and cost element assigned to the vlaue category.