Hi,

Independent requirements are not transferring from SAP to APO. Even we execute the CIF delta report(/SAPAPO/CIF_DELTAREPORT3) because the "send to APO" button is grayed out.

has anyone encountered this before?

Thank you.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

I know you might checked this, but are the material master settings correct? I mean the strategy group etc.

Kedar

Former Member
0 Kudos

Hi Wade,

Senthil is correct to most part. Independent requirements or DP forecast does not integrate with R/3 real time like other orders, stocks etc.

As Senthil said, you need to create a integration model on R/3 side ( transactions CFM1 and CFM2) and then create a transfer job in APO through transaction MC8D, MC8T ( as Senthil described) and then schedule the transfer to R/3.

Thanks.

Former Member
0 Kudos

Hi Wade,

Delta report will not recognize the PIRs for transfer from APO to R/3

If you need to transfer your PIRs from R/3 to APO, use transaction

/SAPAPO/MC8T and create R/3 transfer profile and create a job

in background using transaction /SAPAPO/MC8D

Regards

R. Senthil Mareeswaran.