hi,
can any body throw some light on ETO PROCESS (engineering to order) and hos it will work.
regards,
balaji
We can call ETO as pre sales activity which involves exclusively for new product development, for which there will be a separate department to look after these sort of activities.
=> study feasibility report
=> Inform customer whether the development is feasible or not
=> If feasible, give a quote with development cost
=> If customer approved the quote, ask for tool cost
=> Once tool cost is received, develop a die for tooling
=> Indicate a tentative despatch plan of pilot samples
=> Prepare drawing according to customer spec
=> Submit samples for customer approval
=> If approved, transfer the drawings to delivering plant
=> If not approved, study customer comments and redespatch samples for approval
thanks
G. Lakshmipathi
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello,
Kindly check out the link below:
http://help.sap.com/bp_bblibrary/600/html/E33_EN_DE.htm
Regards,
Sarthak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
95 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.