on 08-25-2009 6:09 AM
Dear All
Is it possible that the budget is only committed only on PO(Purchase Order) not PR(Purchase Requisition) against WBS element?
Hi,
Refer the Note: 955107.
If you mention the transaction group as "++" in the tolerance limit of the AVAC and implement this note: 955107 then the PR commitment is not considered for the AVAC and only PO commitments are considered,
Hope it helps...
Thanks!!!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear
Thanks for your reply, in the tolerence group there is ++ sign if I give only 01 what will be the effect on other groups. Will they commit budget or not?
++ All activity groups
00 Purchase requisition
01 Purchase order
02 Orders for project
03 Goods issue
04 Financial accounting document
05 CO document
06 Budgeting
07 Funds reservation
08 Fixed prices in project
09 Payroll
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
In SPRO>PS>Costs>Budget>Budget Tolerance -
Choose Tr.Group as 01.
Regards
Babu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.