on 08-25-2009 4:57 AM
Hi group members,
One of my customers said that when planning with PP/DS, the product silo's capacity should be considered and if the silo is connected into my customer's customer with a pipeline.
So I'm trying to model this requirements with container resource(storage resource) but how can I create container resource ?
1. Should this be transfered from R/3 or created in APO ?
2. What is the step-wise procedure for this modeling ?
Please instruct me for this.
Regards,
Lee, Seung Won
Yeah, the problem is that you can't really define a container resource in ECC. All work centers are "time based".
Maybe there is an Industry Solution that allows other type of work centers, but I am not sure.
Ken Snyder
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Lee,
You can create and use container resources and model as Multimixed resource
in APO.
1. Should this be transfered from R/3 or created in APO ?
Both ways are possible
2. What is the step-wise procedure for this modeling ?
The following link will guide for creating and integrating
the multimixed resources as container resources
http://help.sap.com/saphelp_scm70/helpdata/EN/dc/85ef3735450b33e10000009b38f842/frameset.htm
Regards
R. Senthil Mareeswaran.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Senthil,
Thanks for your input.
You mean that Should I transfer W/C form R/3 into APO and then define that resource as container resource ?
Or the resource shoud be defined as container capacity category ?
Would you please elaborate for the step ?
Thanks in advance for your cooperation.
Regards,
Lee, Seung Won
Edited by: Jong-Eun Song on Aug 25, 2009 2:15 PM