Actual dates should not impact the Network scheduled dates

Former Member
0 Kudos

Hi

I have planned schdeuled dates (Early/latest).

When i am confirming the activity the actual dates get updated

When i schedule the network the scheduled planned dates are recalulated

This should not happen for this client i am working for

The requirement is that the Planned Scheduled should remain fixed and

should only change if duration, relationship etc changes.

I have tried different option to solve this but still no clue

  • Adjust basic date 1, 2, 3 option

  • Shift Order

  • No date Update - this seems to work but not visible in CN22/CN25/CJ20n

Kindly highlight if any of you have come with similar requirement & provided solution to it

Either thru standard functionality, configuration or any development

Cheers

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

Hi Manoj,

I had the same requirement and able to achieve it by std. settings. Keep in mind that the planned dates wil get changed when you do the final confirmation. You should have the control on the planned dates until the activity get Fianlly confirmed.

psconsultant

Former Member
0 Kudos

Hi Manoj,

I had the same requirement and able to achieve it by std. settings. Keep in mind that the planned dates wil get changed when you do the final confirmation. You should have the control on the planned dates until the activity get Fianlly confirmed.

psconsultant

virendra_pal
Active Contributor
0 Kudos

set schedule in past to 999 and then check - this can be done in scheduling parameters for network OPU6

Former Member
0 Kudos

Hi

Can you elaborate my below querries which may help in identifying a solution to your issue:

1. If your client doesn't want the system to consider Actual Dates, why he wants to Re-Schedule?

2. What he wants to Check/Compare from Network before & after (re)scheduling?

Regards

Babu