cancel
Showing results for 
Search instead for 
Did you mean: 

Transportation Planning Error - u2018No resource for optimizationu2019

Former Member
0 Kudos

Dear All,

While generating the Transportation proposal , I am getting an error u2018No resource for optimizationu2019. Can anyone please guide me what could be the possible reason for the same? Below are some more information:-

1. The resources created by us are getting displayed with the following dimensions.

Weight 40TO, Volume 80M3, Used Qty 0.0, Rem Qty 0.0, Max Utli 0.0, Last Loc u2013 Blank, Multires u2013 false, No. Res. u2013 0, Lock Res u2013 false.

2. The Freight Unit is having following dimensions. Weight u2013 7.770 KG, Volume 38M3, and one container is assigned as a transportation Unit.

3. Source and destination locations both are belonging to same transportation zone for which we have defined one intra-zone land and MTr to which this resource is assigned. This is not a passive resource.

Please advise what could be the possible reason for the same.

Thanks & Regards,

Vikram

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi Vikram,

Please check the following

1) The resource category is "T"

2) The resource is attached to active model 000

3) The resource is attached/assigned to material/item where it is

getting planned.

4) All resource data are maintained properly.

5) Check whether resource is not blocked

Regards

R. Senthil Mareeswaran.

Answers (0)