Delete WBS cost estimate - CKW1/CKW4`

Former Member
0 Kudos

Hi

We are working with project system and based on the customer requirement we create WBS BOM for production of the material and for costing purpose we run Production lot Cost estimate for WBS using transaction CKW1 and activate it using transaction CKW4.

One of our scenario is such that after activating the cost estimate we are making certain changes in the WBS BOM and want to recost the WBS cost estimate(No GR is made yet)

When we are trying to run cost estimate for that WBS and material system is giving us the message that "Cost estimate for this material and WBS is already activated" and not allowing us to proceed with new costing.

We are trying to delete the cost estimate but we can not find out any transaction to delete the cost estimate for WBS element.

How can we delete the existing cost estimate for the WBS element which is already activated.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

This message was moderated.