Time Booked in production order by employee not being displayed in CN48N

Former Member
0 Kudos

Hello Gurus

We have scenario in which manufacturing i.e. Production order (manufacturing) is also involved.

Production orders are being triggered from Network and having assignment of WBS.

Employees involved in production (manufacturing) are booking their time in production order. One can review or see this time in production order information system.

Employees involved in project activities i.e. engineering, design are booking their time in network order using CAT2. This time, after approval are being transferred to project. One can review or see this time in project system information system i.e confirmation overview.

When users are trying to find out actual work in project through CN48N i.e. confirmation overview, time captured in project are being displayed. However, this report is not displaying time booked in production order. This report does show the WBS No, production order no, employee list also. But it is not displaying time booked against employees who have booked time in production order.

Please let us know why time booked in production order is not being displayed ?

Thanks and best regards

Bharat Parikh

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Bharat

Check table for entries -CATSBD

and transaction CATS_DA.

Regards,

PSR

Former Member
0 Kudos

Hi Bharat,

Can you tell us how you confirmed time for employees against Production order?

Report CN48N is to display the Confirmation details of the Network activities of a project. I hope that you have triggered a production order from an activity or network under a WBS element.

Normally the production order confirmations are done using CO11N T-code and already workcenters are assigned in PP.

You can view the confirmation of production order through the report COOIS with selection as Confirmations under List field.

Regards,

Kabir