SD BOM Bill of material

Former Member
0 Kudos

I have created a BOM for SD orders. the main item and the sub-item is assigned to different shipping points because the "loading group" is different in material master data. I want the sub-item to have the same shipping point as the main item in case it is ordered as a set. but there are cases that the sub-item is ordered seperately, in this case material should have the shipping point defined in the material master data.

Is it possible in standart? or should I do it with a user exit in the order?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

It is not pssible in standard functionality, you need to work with user exit only.

Cheers

Chandra