Hi all

my system will not checking budget during creating reservation to WBS( movement 221). System checking the budget during creating reservation to network activities. Please advice need to apply any Sap notes? Recently we applied note for budget checking during GRN and service entry sheet.now it is working fine.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

hi

In SAP reservation is a soft reservation.

Former Member
0 Kudos

hi

but during network reservation system will checking the budget.

varshal_kachole3
Active Contributor
0 Kudos

Hi,

Step 1: Check in Tcode: OPUU, network Tab, if the Res./Purc. req.is selected as Immediately (3) then change it to from release (2).

Step 2: Recreate the scenario.(Create a New project and reassign the Material)

I am sure it will get sorted out.

In your case it looks like PRs were getting created immediately.

There is no provision in SAP where the budget availability control happens at the reservation level.

Hope it helps...

Thanks!!!