on 08-20-2009 5:28 PM
Hi QM experts
I have few lots which are skipped because of dynamic modification rule( the stock is posted to the unrestricted)
But the UD is not done for those inspection lots automatically.
My question is:
1) will the UD for the inspection lot which has a skipped lot will be done automatically and immediately (with delay specidied in the customisation)?
2) Is it necessary to shedule the job for automatic cration of UD?
Please help me to solve this isse. what could be the reson becasue of which the Usage decision is not done for the lot?
Thanks in advace
Hemanth Kumar
hi
1) will the UD for the inspection lot which has a skipped lot will be done automatically and immediately (with delay specidied in the customisation)?
No
You have to schedule it either in QA10-->create varient & run varient through SM36
or
QA16-->create varient
QA17-->schedule
2) Is it necessary to shedule the job for automatic cration of UD?
Yes it is must.UD will not happen in background automatically
Regards
Sujit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.