Hi All,
I am using overall and annual budgeting for a WBS.
I have setup the availability control functionality in my project.
I want to know when we activate the availability control and set up a tolerance limit, it will check availability of on overall budget or on annual budget for a particular WBS?
Is there any specific setting related to it.
regards,
Atul R. Rajmane
First of all you have to select Actvity Control activation type 1 in the project profile. And at the same time you also have to define the availability control whether the budget will check against the value maintained for
1. Overall (or)
2. Overall & relaese (or)
3. Annual (or)
4. Annual & relaese
The budget availablity control also can be inactivated from CJ30 using SETTINGS > AVAILABILITY CONTROL > ACTVATE
C.R. Mohanty
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This message was moderated.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.